Hearing Date June 13, 2002
June 4, 2002 Via Certified Mail
TO:
Honorable California Coastal Commissioners:
The Devil’s Slide Tunnel Project 1st phase ESHA
mitigation (Nov. 2000) construction activities disrupted and blocked the
ESHA water source by “de-watering” the
north frog pond facilitating an unauthorized
“take” of federally listed species CRLF.
The Commission had rejected our appeal in October 2000 as raising “No
Substantial Issue.
CalTrans Devil’s Slide Project commences it’s 2nd
incremental phase by expanding their “habitat transformation efforts”
by implementing massively destructive geotechnical activities with extensive borings, trenching and grading which will destroy/transform the ESHA (
CCC Adopted Findings 1-96) by diverting or blocking the source of the ESHAs
water, aka de-watering the wetlands and
ponds found in the preferred tunnel alignment path . Commission staff now motions a 2nd time, appellant raises No
Substantial Issue in CalTrans current destructive incremental phase of the Devil’s Slide Tunnel Project.
Staff’s contentions not only contradicts the CCC
Adopted Findings LCP 1-96 for the Devil’s Slide Tunnel Project ESHAs , staff’s
contentions are made without factual
and legal bases to support their contention that our appeal raises “No
Substantial Issue”. Staff has provided NO factual or legal bases to contend
that this geotechnical incremental phase is exempt from the Adopted
Finding for the Devil’s Slide Project LCP 1-96. A “YES” vote in support of “No Substantial Issue” will signal the
entire State that the that destruction of ESHAs in the early phrases of a
development project is permissible
under the Coastal Act. The Foundation’s “ESHA PROTECTION” appeal speaks for itself and
clearly cites the inconsistencies with respect to specific LCP policies and
documented incremental and cumulative impacts to environmentally sensitive
habitat areas and cites allegations of
the specific impacts from the geotechnical exploratory borings, trenching and
grading which are part of the 2nd phase of this approved project. We
respectfully request a NO vote on
staff’s motion and request that the Commission hear the appeal application de
novo.
APPEAL
NO: A-2-SMC-02-013
APPLICANTS: California Department of Transportation
AGENTS: Skip Sokow, Project Engineer
LOCAL
GOVERNMENT: San Mateo County
LOCAL
DECISION: Approval with Conditions
PROJECT
LOCATION: Highway 1, Devil’s Slide
Tunnel Project, south of Pacifica,
San Mateo County.
PROJECT DESCRIPTION: “The overall project consists of three distinct parts: investigative
borings for the north portal bridge, borings and trenching along the proposed
tunnel alignment and borings with the proposed disposal area.” Quotation from SMC document dated April 10,
2002 County File # PLN-2001-00799 (CalTrans)
APPELLANT:
Half Moon Bay Coastside Foundation aka Save Our Bay
Foundation ,Oscar Braun, Executive Director
SUBSTANTIVE FILE:
San
Mateo County PLN 2001-00799 (CalTrans)
APPELLANT RECOMMENDATION:“ESHA Protection” SUBSTANSIAL ISSUE
APPELLANT EXECUTIVE SUMMARY
1.0 On January 9, 1997, The
California Coastal Commission held a public meeting and voted 9-0 to certify
San Mateo County LCP Amendment No. 1-96 as submitted by the County. The
Amendment incorporates the Provision of Measure T, the Devil’s Slide Tunnel
Initiative, into the Land Use Plan Portion of the LCP. The San Mateo County LCP
Amendment No. 1-96 (Devil’s Slide Tunnel ) shall be consistent with the Coastal
Act and “require that the roadway improvements be consistent with policies
of the Local Coastal Plan, particularly the Sensitive Habitats and
Agricultural Components (Policy 2.54c).” The protection of Sensitive
Habitats is the primary Substantial Issue of this appeal.
2.0
Wetland and ESHA Impact Substantial Issues: Neither CalTrans nor the County of
San Mateo have provided factual or legal support for the local government’s decision
that this approved project is consistent
with the certified LCP by AVOIDING ADVERSE IMPACTS to wetlands or ESHAs
and with the public access policies of the Coastal Act. CalTrans geotechnical
borings, trenching and grading approved project will adversely and
significantly impact by “draining and de-watering” ESHAs and will destroy
habitats of rare and endangered species; ergo does not conform with LCP policies 7.7, 7.11, 7.14,
7.18, 7.1, 7.3, 7.32, 7.33, 7.34 and
7.35 and is inconsistent with the land use policies of the LCP. This
approved project is conditioned on ESHA “mitigation schemes” that have resulted
in a “take” of federally listed Rana Avrora Draytonii (Red Legged Frog). Take is defined by the Endangered
Species Act as “ to harass, harm, pursue, hunt, shoot, wound, kill, trap,
capture, or collect any listed wildlife species. “Harm” in this definition includes significant habitat
modification or degradation (de-watering) where it actually kills or injures
wildlife, by significantly impairing essential behavioral patterns, including
breeding, feeding, or sheltering. (50 CFR & 17.3). CalTrans geotechnical
borings, trenching and grading does not provide any avoidance of destructive impacts. Caltrans
geotechnical approved project provides
only on-site and off-site mitigation schemes.
The California Court of Appeal in 1999 found that “on-site or off-site
mitigation” is not consistent with the LCP or Coastal Act under Section 30240. CalTrans committed a “take” of listed
federal species while constructing their CRLF mitigation pond in preparation
for this geotechnical project. An unauthorized “take” is a violation of the
Endangered Species Act , LCP and Coastal Act and could disqualify this approved
roadway project from receiving Federal permits or $275 million in FHWA funding.
3.0 Neither CalTrans nor the County of San Mateo have provided factual or legal support for the local government’s decision that this approved project is consistent with the certified LCP by AVOIDING IMPACTS that would either permanently block or destroy (de-watering) the spring sites that serve as the water source of the ponds, cause siltation in the ponds or temporarily disrupt adjacent upland foraging retreat area for the frogs while conducting their geotechnical boring, trenching and grading activities in the North Portal ESHAs. The CCC 1997 LCP 1-96 Adopted Finding stated: “Construction of the North Portal approach road could fill portions of the two red-legged frog ponds in that location. Even constructing a bridge that did not directly fill the ponds would adversely affect the red-legged from by shading portions of the pond during most of the day, thereby reducing the basking opportunities for frogs and possibly lowering the spring pond water temperatures. The latter could in turn affect the development of time of frog eggs and larvae. Any one or combination of the above possible events could result in the “reduction or negation of the red-legged frog population at the site.” Furthermore, construction and grading activities for the bridge could either permanently block or destroy the spring sites that serve as the water source of the ponds, cause siltation in the ponds, and temporarily disrupt adjacent upland foraging/ retreat area for the frogs..” ( SMC LCP 1-96 page 18). CalTrans geotechnical borings, trenching and grading activities will destroy the springs sites and cause an additional “take” of federally listed endangered species (Red Legged Frog).
4.0 Neither
CalTrans nor the County of San Mateo have provided factual or legal support for
the local government’s decision that this geotechnical projects borings,
trenching, grading and hauling construction activities are consistent with the LCP policy 7.34 and 7.35. Policy 7.34
states, among other things, that “any development must not impact the
functional capacity of the habitat”. and recommend mitigation if development is
permitted within or adjacent to identified habitats of rare and endangered species. “Policy 7.35 states that the County must require preservation of all habitat of rare and endangered species…”
Thus, an applicant for the tunnel project (ie: or any portion there) would need
to demonstrate how the particular design chosen for any necessary fill for the
tunnel project will ensure the habitat of the red-legged frog is not
compromised.”( Adopted Findings SMC LCP 1-96 page 23)
4.1 In November 2000 CalTrans demonstrated how their preferred alternative Tunnels/Bridges geotechnical borings, trenching and grading activities WILL adversely impact the functional and biological capacity of the environmentally sensitive habitat area (ESHA) and WILL ensure the habitat of the red-legged frog is adversely compromised. On November 24, 2000, Save Our Bay Watershed Posse staff conducted a native species field survey at the location of the CalTrans Tunnels/Bridges geotechnical on-site & off-site mitigation construction site , Devil’s Slide Highway 1 Project site, Pacifica, San Mateo County, California. After the three hour native species field survey was concluded, (attached please find survey form for dates 7/27/000 & 11/24/000) it was found by SOB staff that the Tunnels/Bridges mitigation project activities conducted by Caltrans, their agents or others has resulted in a “take” of federally listed Rana Avrora Draytonii, .. aka California Red-Legged Frog. Take is defined by the Endangered Species Act as “ to harass, harm, pursue, hunt, shoot, wound, kill, trap, capture, or collect any listed wildlife species. “Harm” in this definition includes significant habitat modification or degradation where it actually kills or injures wildlife, by significantly impairing essential behavioral patterns, including breeding, feeding, or sheltering. (50 CFR & 17.3)The Foundation’s Executive Director reported the take to Sheila Larson of the U.S. Fish & Wildlife Service on Friday the 24th of November by telephone that their authorized mitigation ESHA mitigation scheme had cause the north pond to be “de-watered” thus facilitating a unauthorized “take”. On Monday November 27th, by telephone, Oscar Braun filed the notice of violation with U.S. Fish & Wildlife Service Agent Scott Pierson and provided him via fax the field survey forms and mitigation project site location map. The Foundation also informed agent Pierson that they have photos of the ESHA starting 7/27/2000 up to and including 11/24/2000. On the 24th, the Foundation also notified the California Department of Fish & Game and San Mateo County Environmental Services Agency. (CCC Notice of Violation attached). Unauthorized “take” may disqualify this approved project from receiving Federal permits and the needed $275 million in FHWA highway construction funding. Neither CalTrans nor the County of San Mateo have provided factual or legal support for the local government’s decision that this geotechnical projects borings, trenching, grading and hauling construction activities are consistent with the LCP policy 7.34 and 7.35.
5.0 Appellant Response to CCC Footnote #3 on
page 5 of Staff Report:
“The Commission approved the plan to relocate the
CRLF as part of the October 2000 federal consistency determination with respect
to the tunnel project. The Commission
separately determined at the October 2000 hearing that an appeal by Oscar Braun
and Save Our Bay Foundation of the County’s coastal development permit for the
CRLF pond on Shamrock Ranch (A-2 SMC-00-35, PLN 2000-00536) raised no
substantial issue” The authorized off-site frog pond tunnel project mitigation and
relocation of the CRLF facilitated the unauthorized “take” of the CRLF as anticipated and proposed to the
County of San Mateo by Lennie Roberts. On
August 23, 2000, Lennie Roberts,
renowned lobbyist/professional land use planning consultant and leading
proponent of the Devil’s Slide Tunnels/Bridges/Filling/Mitigation alternative,
addressed the San Mateo County Planning Commission in support of Caltrans’ frog
pond Tunnels/Bridges/Fill/Mitigation project. Below is the entire transcript of
Ms. Roberts comments.
5.1 “Good Morning Mr. Chairman, I’m Lennie Roberts
speaking for the Committee for Green Foothills, and we support this project.
Aaaa, it would be nice to have had something in the staff report to the fact
this is being done in conjunction with the U.S. Fish & Wildlife Service and
because this has been a long negotiated process with the CalTrans engineers and
the U.S. Wildlife Service. How they’ve been in consultation with the frog and
other issues, “this is mitigation for the Tunnel” and so I think it would be helpful if we put that
somewhere because it is part of a very broad extensive process that has gone
through with the tunnel construction. So, so this is one of the issues that
occurs with the endanger species is that if you are going to “take”
the endangered species or effect their habitat and you’re going to first do “mitigation” to
first avoid the impact aaa which
the Tunnel project has done to the greatest degree possible by building a
bridge over this valley. Originally
this valley was going to be filled to go across, so that would have impacted
the frog pond habitat, so they’re bridging
instead and they’re creating this new frog habitat and one of the issues
always is ...will that work? And by doing this ahead of time, ahead
of the project itself , a there will be, I think ,sufficient assurance that the
project will be a successful “mitigation”! We hope so...a
perhaps one thing you might want to put in here is the additional condition
that there will be monitoring of project as it goes through the construction
and afterwards to make sure that the re-vegetation is successful and that the
habitat is successfully established. I think that would be a good conditional
condition to put in there. So we are very supportive of this and we appreciate
the County expediting this and I know everybody is trying to expedite this
project, in spite of everybody’s attempts it has taken a lot longer than
everybody thought . Aaa so those are my comments and yeah I believe that the way they capture the frogs is at
night with flash lights , a time honored technique (laughter) or the tadpoles
in the spring time. But to successfully get the adults you have to do that I
believe. Thank you.
.The above noted
Notice of Violation record clearly shows that County of San Mateo approved
Tunnels/Bridges ESHA mitigation project scheme
failed and DID NOT AVOID ADVERSELY IMPACTING the ESHAs as required by
the LCP policies 7.34 and 7.35. The
Commissions finding of “No Substantial Issue” in October of 2000 facilitated
the unauthorized “take” and dewatering
of the north portal pond in November 2000.
The Commission staff did not provide
the Commission with the degree
of factual and legal findings required
to support the local government decision that on-site or off-site
mitigation was consistent with the certified LCP or that CalTrans approved
geotechnical borings, trenching and grading won’t continue to destroy by
de-watering the approved geotechnical project
ESHAs.
6.0 Appellant
Response to CCC Footnote #2 on page 5 Staff Report:
“Adopted findings made by the Commission in
certifying the Measure-T amendment in January 1997 recognized
that the proposed tunnel alignment would result in the fill of wetlands,
including the wetlands near the South Portal, and a finding made pursuant to
Coastal Act Section 30007.5 that given the importance of Highway 1 for public
access the tunnel project nevertheless on balance was most protective of
coastal resources.” Neither the Commission nor
San Mateo County have provided factual
or legal support for the local government’s decision that the destruction of
wetland and ESHAs is consistent with
the LCP or Coastal Act by making a finding pursuant to Coastal Act Section
30007.5. Commission staff footnote is incomplete
and thus erroneous. The Commission staff are citing the findings adopted in 1997 in the CCC Staff Report, San Mateo
County LCP No. 1-86 (1997), CCC Staff Report No. 1-96, pp 24 (1997), CCC Staff
Report No.1-96, pp.28-29 (1997). Those
findings were found inconsistent by the
California Court of Appeals in
1999. The Court’s Bolsa Chica
Land Trust ruling clearly found against the Commission use of 30007.5 as
“inconsistent with the Coastal Act” in the resolving of conflicts among
competing Coastal Act policies under Section 30240 . “The reasoning
Commission employed is seductive but, in the end, unpersuasive. The
interpretation was not contemporaneous with enactment of section 30240 or the
result of any considered official interpretative effort and it did not carry
any other of the indicia of reliability which normally requires deference to an
administrative interpretation. Secondly, the language of section 30240 does not
permit a process by which the habitat values of an ESHA can be isolated and
then recreated in another location. Rather,
a literal reading of the statue protects the area of an ESHA from uses which
threaten the habitat values which exist in the ESHA. Importantly, while the
obvious goal of section 30240 is to
protect habitat values, the express terms of the statute do not provide that
protection by treating those values as intangibles which can be moved from
place to place to suit the needs of development. Rather , the terms of the statute protect habitat values by
placing strict limits on the uses which may occur in an ESHA and by carefully
controlling the manner uses in the area around the ESHA are developed. The
Commission has decided that an area is an ESHA, section 30240 does not itself
provide Commission power to alter its strict limitations. There is simply no
reference in section 30240 which can be interpreted as diminishing the level of protection an ESHA receives
based on its viability. Rather, under the statutory scheme, ESHA’s whether they
are pristine and growing or fouled and threatened, receive uniform treatment
and protection. In short, while compromise and balancing in light of
existing conditions is appropriate and indeed encouraged under other applicable portions of the
Coastal Act, the power to balance and compromise conflicting interest cannot be
found in section 30240.” Environmentally Sensitive Habitat Areas
(ESHAs) are afforded the highest level of protection under the LCP and Coastal
Act. If the Commission finds that these
ESHA protections do not qualify as a “Substantial Issue” and that the power to
balance and compromise conflicting interest within the LCP or Coastal Act, then
the Commission will set a new precedent
for future interpretations of it’s LCP.
This appeal raises a Substantial Issue that will have statewide
significance. The Commissions 1997
Adopted Findings cited were found inconsistent
by the California Court of Appeals in
1999. The Court’s Bolsa Chica
Land Trust ruling clearly found against the Commission use of 30007.5 as
“inconsistent with the Coastal Act” in the resolving of conflicts among
competing Coastal Act policies under Section 30240
6.1 By
letter dated May 11, 1999, Paul Koenig, Director of Environmental Services
for the County of San Mateo, notified CalTrans “The FEIS/EIR on pages 74
and 75 describe the impacts of the proposed tunnel on wetland and riparian
habitats. We want to bring to your
attention the potential conflicts between this discussion and the Coastal Act
and Local Coastal Program. The tunnel
will fill approximately 5,500 square feet of wetlands and 9,700 feet of riparian
habitat. Off-site mitigation of
such an impact is not currently allowed under the Coastal Act or Local Coastal
Program. As a result, we cannot at this time find that the proposed tunnel
design complies with the Local Coastal Program.”
6.2 By
Letter on May 12, 1999, Jack Liebster, Coastal Planner for California
Coastal Commission, advised CalTrans of the Commission staff’s principal
concerns. Of particular
note is his discussion of the impact of the tunnel project on
the wetlands and his conclusion that “ the County, and the Commission, if the project is
appealed, will have to assess the appropriateness of any fill proposed in
wetlands as defined under the LCP using wetland policies.” He further states: “It is not clear that
the proposed use of wetland areas as a site for which the LCP indicates fill
can be allowed. In addition, the LCP wetlands policies require an
examination of alternatives to projects which impacts wetland fill.”
7.0 Conclusion: CalTrans mitigation
scheme has demonstrated that their preferred alternative design for
Tunnels/Bridges/Fill/Mitigation project
will negatively impact the
functional and biological capacity of the environmentally sensitive habitat
(ESHA) and will cause the elimination or degradation of the habitat of the
endangered species red-legged frogs in the
ponds area under the Tunnels/ Bridges on Shamrock Ranch. The environmental sensitive habitat of the
red-legged frog has been negatively compromised resulting in an
unauthorized incidental “take” by
CalTrans while attempting to implement their “ ESHA mitigation scheme” for the
Devil’s Slide Tunnels/Bridges/Fill/Mitigation Project Alternative. CalTrans has demonstrated that their fill
and ESHA mitigation schemes places the Shamrock Ranch frog ponds and ESHAs
located listed endangered species in “jeopardy” and is inconsistent with the
San Mateo County LCP.
The Coastal Act and the San Mateo County Local
Coastal Program requires CalTrans to explore the “No Project” alternative as
most protective and least environmentally damaging. The “No Project” alternative could mean taking no action, or
possible intensifying efforts to dewater the landslide at Devil’s Slide. As the highly respected San Mateo County
Consulting Geologist Victor H. Abadie III stated in his April 27, 2002 appeal letter to the San Mateo Board of Supervisors: “Dewatering the landslide
and repairing the existing roadway violates no law, create no impact on the
wetlands or ESHA, and are is explicitly authorized under the San Mateo County
Measure-T Local Coastal Program.
Lastly, a geotechnical study of the current Devil’s Slide Hwy 1 route
will violate no wetland laws, because there are no wetlands or ESHAs on the
current Route 1 alignment itself.” The San Mateo County Local Coastal
Program requires that the preferred alternative be the most protective and
least environmentally damaging alternative.
The “No Project” alternative (aka
repair/dewatering of the current Devil’s Slide Route 1 alignment) is the
“least environmentally damaging feasible alternative” and therefore is
the ONLY alternative “Consistent” with the CCC certified Measure-T
Amendment 1-96 of the Local Coastal
Program for the San Mateo County Devil’s Slide Route 1 Improvement Project. We
ask the California Coastal Commission to declare our appeal as raising
“Substantial Issues” and uphold our Appeal
of San Mateo County CDP File Number PLN
2001-00799 and Deny CalTrans their CDP for their Devil’s Slide Highway 1 Tunnels/Bridges/Fill/Mitigation
Alternative project design.