AD1Thursday, March 28, 2002

 

 

 

The weather is
P/Cloudy

 

 Temperature

48° F

 

 

 

 

Question of the Week

What was your favorite movie of the past year?

A Beautiful Mind

Lord of the Rings

Gosford Park

Moulin Rouge

In The Bedroom

Shrek

Monsters, Inc.

None of the above


 

- Search The Web-

 

Tunnels' price tag skyrockets


Devil's Slide circa 1915 when they were building the roadway.

By Eric Rice--Half Moon Bay Review

An updated cost estimate for the Devil's Slide tunnels project puts the pricetag at almost twice the estimate when the tunnel was first studied.

The California Department of Transportation (CalTrans) now estimates the cost of the Devil's Slide tunnels project at about $270 million - $230 million for construction and $40 million for design and other non-construction costs.

What this will mean for the project's chances of getting funding is uncertain. A clearer picture may emerge in the next few weeks when CalTrans expects to receive final approval for the final environmental impact statement (EIS) for the tunnels.

Marc Roddin, who has been tracking the tunnels project for the Metropolitan Transportation Commission, was not especially alarmed by the jump in cost. He said federal officials have been monitoring the project closely and if they approve the EIS they will also, in effect, be signing off on the new cost estimate.

Both CalTrans staff and Bill Wong project leader with the FHWA, which is responsible for approving the EIS, predict that the EIS will be approved. Wong said it could happen in as soon as two to three weeks, though previous predictions by CalTrans and FHWA have fallen far short.

For almost five years highway planners have been estimating the cost of the project at about $150 million. But Skip Sowko, project manager for CalTrans on the tunnels project, said that inflation accounts for a substantial amount of the increase.

The previous estimate was based on the project beginning construction in 1997. The current timetable now puts it in late 2003 or early 2004.

"A large portion of it is simply escalation (of costs due to inflation)," Sowko said.

He said revisions involving changes to cuts in the mountain, the entry portals, and avoiding wetlands also drove up the cost. Also, the general bidding climate for transportation projects is not as favorable today as it was in 1997, Sowko said.

CalTrans and the county propose drilling two 4,000-foot-long single-direction tunnels side by side through San Pedro Mountain to replace a section of the existing Highway 1 alignment, which has periodically suffered slippage and landslides since it opened in 1937.

The new estimate has not been released yet by CalTrans, but is included in a revised environmental impact statement (EIS) prepared for the project. As part of an extensive review of the environmental aspects of the document, the FHWA required that CalTrans also update the cost estimate.

Even staunch tunnel supporters were taken aback at the dramatic increase.

"Holy cow!" reacted Zoe Kersteen-Tucker, an environmental leader in helping plan the tunnels.

"This will probably raise some eyebrows," Kersteen-Tucker said. "It's raising mine."

But she reiterated her support for the tunnels.

"What are our choices? Dewatering is not permanent. That's throwing money away. No, I'm not backing down. We need to build this."

In 1999 Congress granted the tunnels project emergency funding as part of a huge transportation funding bill called TEA-21. The funding is supposed to be available when the project is ready to begin construction.

With TEA-21 funding, the tunnels won't have to compete with other local projects for funding.

A figure as high as $270 million is bound to make someone in the federal government sit up and take notice, predicted Michael Murphy, an advocate of a different kind of project called dewatering.

"How can anyone honestly believe anybody is going to spend that much?" Murphy reacted. "I just think that means it's deader than a doornail. At some level, somebody is allocating scarce resources" to the tunnel instead of other needed projects, Murphy said.

Although agog at the size of the increase, Kersteen-Tucker and environmental activist Lennie Roberts both emphasized that cost increases are routine in virtually all transportation projects. Replacing a section of the Bay Bridge to make it earthquake-safe, for example, doubled in price over the course of a few years, but it is still proceeding forward.

But both were surprised by the size of the increase in the cost of the tunnels.

"I suppose every transportation project ever proposed has gone through a surprise like this," Roberts said.

The increase is certain to provide fodder for some of the tunnels project's critics. The campaign slogan for the tunnel project - "Sooner. Safer. Cheaper." - has regularly been revived by critics who say time has already disproven the sooner part of it.

Roberts defended the tunnels project by saying, "It probably still is cheaper than the bypass."

Sowko also stressed that CalTrans is committed to the tunnels. He noted that the bypass would include 11 structures and expensive, enormous cuts in the mountains. He also said CalTrans still believes "Dewatering is not a permanent solution."

"All the elements we have in (the tunnels EIS) are needed, and the project has been identified as needed," Sowko said.

Roberts predicted that once the public gets over the "initial sticker shock in something like this," the tunnel will continue its march toward construction.

"This project has a huge head of steam and I know how hard it is to turn a project in a different direction, having been in that position," said Roberts, who fought CalTrans' efforts to build an inland bypass for 25 years before it was forced by voters to abandon the bypass.

Criticism of the tunnels has remained persistent, although it has been limited to a small group of people.

Advocates of dewatering, a technique of stabilizing the mountainside by removing water inside it that weighs it down and causes slippage, want CalTrans to fix the existing alignment of Highway 1. They maintain that dewatering could be accomplished for a fraction of the cost of the tunnels. Murphy urged CalTrans to spend $100,000 on a feasibility study of dewatering.

Murphy and others point to dewatering projects in other states and at Devil's Slide by CalTrans four years ago. That work is credited with helping Devil's Slide weather one of the wettest winters on record without serious slippage as indicative of its potential.

CalTrans studied dewatering in-house as part of the EIS update and concluded it would not work. Among the agency's concerns was the fractured nature of the rock in the slide-prone area of the mountain, which makes it difficult to remove large amounts of water, and erosion by the ocean undercutting the highway.

In 1996 when the first detailed estimate to build a tunnel through San Pedro Mountain was made the cost was put at between $131 million and $150 million. The consultant that arrived at that figure, Woodward-Clyde, said at the time that figure was "upper boundary" and could be expected to decrease as much as 10 to 15 percent as designs were fleshed out and estimates refined.

Roberts attributed some of the cost increase to delays caused by Half Moon Bay resident Oscar Braun. Braun has promised all along that he will sue to halt the tunnels. He lost one court challenge already, but continues to threaten CalTrans, the county and the Coastal Commission with additional lawsuits if the EIS is certified.

His threats are apparently being taken seriously. According to a member of CalTrans' environmental staff, one of the reasons the Federal Highways Administration has been unusually attentive to even the smallest details in the EIS is because of the threat of a lawsuit by Braun.


 



AD3



AD5


 



Copyright 2002 Half Moon Bay Review and Pescadero Pebble.